I-5/Deschutes Road NB Off-Ramp

Description: In Anderson at the Deschutes Road Interchange. The project includes construction of a new off-ramp from northbound I-5 to Deschutes Road, widening a portion of the northbound I-5 on-ramp, and constr

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Anderson
Zip Code 96007
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
 
County/State Route Shasta 5
Postmile Begin/End R  4.7 R  4.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  630    630  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Anderson Jeff Kiser (530)378-6636   jkiser@ci.anderson.ca.us
Design (PS&E) Phase
City of Anderson Jeff Kiser (530)378-6636   jkiser@ci.anderson.ca.us
Right of Way Phase
City of Anderson Jeff Kiser (530)378-6636   jkiser@ci.anderson.ca.us
Construction Phase
City of Anderson Jeff Kiser (530)378-6636   jkiser@ci.anderson.ca.us
 
Corridor System Management Plan
City of Anderson Jeff Kiser (530)378-6636   jkiser@ci.anderson.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$6,000 $0 $6,000
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$1,275 $0 $1,275
Non Budgeted ETC
$0 $0 $0
 
Total**** $7,275 $0 $7,275

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$475 $0 $475 $475
Design(PS&E)
$400 $0 $400 $400
Right of Way
$400 $0 $400 $400
Construction
$6,000 $0 $6,000 $5,979
 
Total* $7,275 $0 $7,275 $7,254

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  07/01/2003 

11/30/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2011 

04/01/2012 
 

 
05/01/2011 

04/01/2012 
100  05/01/2011 

04/23/2012 


-1 
Begin Right of Way Phase

End Right of Way Phase
05/01/2011 

03/15/2012 
 

 
05/01/2011 

03/15/2012 
100  05/01/2011 

04/23/2011 


11 
Begin Construction Phase

End Construction Phase
06/05/2012 

12/15/2012 
 

 
06/05/2012 

12/15/2012 
100  07/17/2012 

11/19/2013 
-1 

-11 
Begin Closeout Phase

End Closeout Phase
12/15/2012 

05/01/2013 
 

 
12/15/2012 

05/01/2013 
100  11/20/2013 

06/26/2015 
-11 

-26 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 630 630

Bond Funding Cost
Adopted:
$6,000,000
Current Approved:
$6,000,000
Actual Expenditures:
$5,979,000

 

Status as of December 31, 2023.